1. If any urupā, traditional sites, taonga (significant artefacts), or kōiwi (human remains) are exposed during site works, then the following procedures shall apply:
2. The works shall be designed and constructed to limit the EMF exposure at or beyond the secure boundary of the substation site to the International Commission on Non-Ionising Radiation Protection Guidelines for limiting exposure to time-varying electric, magnetic, and electromagnetic fields (up to 300 GHz) (Health Physics, 1998, 74(4): 494–522) (ICNIRP Guidelines) public reference levels of 5 kV/m for electric fields and 100 µT for magnetic flux density at one metre above ground level under maximum normal operating conditions (ie, when there are no faults in the transmission system).
3. All works shall be designed to comply with NZS 6869:2004 Limits and Measurement Methods of Electromagnetic Noise from High-Voltage a.c. Power Systems, 0.15 to 1000 MHz.
4. In designing and constructing the work, Transpower shall give consideration to third-party conductive services to ensure compliance with regulations 58, 60, 69 and 87 of the Electricity Regulations 1997 as in force at the date of confirmation of the designation.
5. Substation earth grids shall be designed, built, and tested to ensure electrical safety at or beyond the designation boundary in accordance with Transpower Standard TP.DS.52.01, Issue 2, January 2005.
6. All exterior lighting shall be designed to comply with:
(a) AS/NZS 1158 Lighting for Roads and Public Spaces 2005 Part 3.1; and
(b) Transpower’s Requirements for Outdoor Switchyard Lighting Policy, TP GS 41.01, Issue 3, April 2006; and
(c) AS 4282 1997, Control of Obtrusive Effects of Outdoor Lighting.
7. Any new equipment (such as transformers, fans and circuit breakers) required as part of the Upper North Island Grid Upgrade Project shall be designed and operated to ensure that the following noise limits shall not be exceeded:
8. Sound levels shall 0be assessed in accordance with NZS6802:1991 Assessment of Environmental Sound.
9. A design report shall be provided to the satisfaction of the Manukau City Council prior to the installation of any new noise generating substation equipment that demonstrates compliance with these limits.
10. Within one month of installation, the new equipment shall be assessed at source for its sound power level using EN60076-10:2001-05 Power Transformers Part 10 Determination of Sound Levels. Sound levels shall then be predicted at the designation boundary. Monitoring and prediction shall be undertaken by a suitably qualified and experienced person within one month of the commissioning of any new equipment. The results of the noise monitoring shall be made available to the Manukau City Council upon request.
11. Transpower shall review the noise levels and report to Manukau City Council at the time of each designation roll-over on progress that has been made to reduce noise levels progressively as a result of any necessary replacement of transformers.
1. The existing noise levels at the Otahuhu Substation (except for construction and maintenance works) have been predicted as 52 dBA L10 at Nos 8, 12 and 16 Waipapa Crescent. These sound levels contain special audible characteristics and an assessment using NZS6802:1991 would cause any performance standard to be reduced by 5 dB.
12. Vibration from all construction activities shall not exceed the limits of, and shall be measured and assessed in accordance with, German Standard DIN 4150-3 (1999-02) Structural Vibration – Effects of Vibration on Structures.
13. Any part of the facility containing oil shall be designed to comply with Transpower’s Oil Spill Management Policy (TPG:GS.54.01), Issue 2, June 2002.
14. At least 30 days prior to commencement of any construction activity on the site, Transpower shall submit a construction management plan to the Council’s Consents Officer. The Council’s Consents Officer shall respond within 20 working days indicating whether approval is given or refused. Approval shall not be unreasonably withheld. The construction management plan shall detail:
15. Subject to condition 16, all construction and maintenance work shall be designed, managed and conducted to ensure that construction and maintenance noise from the site does not exceed the limits in NZS6803:1999 Acoustics–Construction Noise at locations set out in section 6.2 of that standard.
16. The noise limits shall not apply to emergency work required to re-establish continuity of supply, work urgently required to prevent loss of life or other personal injury, or commissioning works at the substation site, but all practicable steps shall be undertaken to control noise and to avoid adverse noise effects, particularly at times when the stricter noise limits apply (eg, at night-time).
17. Prior to any significant construction work taking place, including any earthworks, a noise management plan shall be prepared, with the assistance of a suitably qualified and experienced person, that sets out the management procedures in terms of section 8 and Annex E of NZS6803:1999 and the works shall be undertaken in accordance with that noise management plan.
18. The noise management plan required by condition 17 shall be submitted to Council’s Consents Manager for approval, at least 20 working days prior to the works commencing. The Council’s Consents Manager shall respond within 20 working days indicating whether approval is given or refused. Approval shall not be unreasonably withheld.