Obviously cost will be a significant factor in choosing a technical solution. There will be ongoing maintenance and operating costs that will need to be paid for. The relative costs of different on-site systems are discussed in Appendix 6. The more general issues of funding are discussed here.
Traditionally, wastewater systems have been managed in two ways. The first is where on-site or individual systems have been managed by the householder or stand-alone business. The construction, maintenance and operation of the system lie with the individual. In contrast, centralised collection and treatment systems are managed by a central agency, usually the local authority, which undertakes all management activities in a co-ordinated approach to wastewater servicing. This has normally been the practice on a regional or district or cluster approach to management of community-wide wastewater schemes. Occasionally, responsibility would be transferred to a separate agency, which would be governed in some way by the local authorities concerned. Auckland region's Watercare is an example of this.
However, there is an international trend towards placing on-site wastewater systems under integrated management programmes, particularly with respect to their operation, maintenance and monitoring. This trend is becoming evident in some areas of New Zealand, and is the recommended approach in the joint Australian/New Zealand Standard (2000) for on-site domestic wastewater management.
The newer cluster systems can be managed by a local authority (if they constructed them) or by a corporate entity. The latter would be set up by the property owners to manage the system on their behalf. This 'centralising' of management reflects both the need to have a clear line of responsibility and the complexity of the systems being managed.
So a more comprehensive picture of wastewater systems management can look something like that outlined in Figure 11.1.
The individual household management of on-site systems has come under increasing scrutiny by agencies concerned about public health. It is common to find that septic tanks and other on-site systems are poorly maintained and operated. There are often consequent problems with discharges on to land and waterways, and contamination of the water supply. Sometimes the cause of failure is lack of information about how to operate and maintain the systems. Sometimes it is an issue of cost.
Another problem is that failure to maintain the on-site system can mean that its 'life' is drastically reduced. The homeowner may save money in the short term, but the system may have to be replaced earlier than normal. The value of the asset is lost. This recent scrutiny is likely to force communities who are otherwise comfortable with their on-site systems to review the situation.
One of the problems with this on-site system failure is that it can push a community into choosing off-site cluster or centralised systems. This physical technical system may not be necessary if the on-site systems are well managed.
There are two types of management solution you can consider when you explore technical solutions.
For example, your bach settlement might consist of 100 houses, all with septic tanks. Fifty of these houses have permanent residents and 50 have summer visitors, who have limited knowledge of septic tank systems. One solution may be for the owners to get together and pay a third person to monitor and maintain these systems for a set price. Capital costs to upgrade and repair a particular septic tank would still be the responsibility of the individual land owner.
The majority of the community may feel that some regulation to require management of the on-site systems is necessary. Or your community may want to clearly indicate the expected standard for any new people settling in the area. A simple way to do this is to require everyone to perform to a certain level. This two-pronged approach may reduce pressure to move to a centralised technical system because the management of the on-site systems is faulty.
Such integration can:
This concept of integrating the management of on-site systems is referred to overseas as 'decentralised wastewater management' (DWM). The objective of DWM is to provide centralised management of decentralised facilities, such as on-site septic tank and soakage trench systems on individual properties. This means that a level of management service equivalent to that of centralised and cluster wastewater systems can be accomplished. Sometimes overseas this DWM can include investigation and design of the system.
This approach to operating and maintaining on-site systems would still need the householder to take some responsibility; for example, making sure that toxic substances do not enter the system.
In 1999 Environment BOP introduced a system of on-site wastewater system inspections for properties at 14 coastal communities in the Tauranga Harbour and Rotorua Lakes areas. There was concern that the high density of residential development and un-maintained septic tank effluent soakage systems were contributing to environmental effects on natural water quality. To initiate the programme, Environment BOP ran training courses for prospective certifiers, who were recruited from the drainlaying and tank-servicing industry. All homeowners in the community areas were given ample information on the reasons for and the method of carrying out the inspections, and advised that following a satisfactory inspection, a compliance certificate would be issued. Those systems that required remedial work to bring them up to a satisfactory standard would be certified following completion of the work. A deadline was set for homeowners to engage a certifier and have the inspections completed, whereupon certificates would be issued by Environment BOP.
The on-site system inspection process involved lifting the lid of the septic tank, pumping the tank out, inspecting its size and structural condition, and checking out the condition of the soakage field. In addition, the location of the system in relation to environmental features on the site (such as groundwater level, nearness to streams, water courses, lake and harbour sides, as well as site boundary conditions) were noted and reported on. A scoring system based on demerit points associated with non-compliance with regional rules for on-site system installation was used to rank the suitability and performance of each system. Payment for the inspection and septic tank pump-out was arranged directly by the owner through the certifier who arranged all the work. A fee was recovered by the certifier to pay Environment BOP for the issue of the compliance certificate, as well as administration costs, including auditing of inspections.
The inspection programme indicated that several settlements needed to change to a community sewerage scheme. For the remaining localities, inspections are to continue at three-yearly intervals.
There are different levels of management associated with the use, operation and maintenance of on-site systems involving householders, owner body corporate agencies, or local authority agency. Examples are as follows.19
Level 1: leave all responsibility for O&M management in the hands of householders, but the local authority develops an inventory of systems, and provides information to owners and users on a regular basis.
Level 2: inspection and maintenance certification agree a standard of maintenance, which would be carried out by an external operator engaged by the householder. This would require the council to set a consistent standard across all the systems in an area, which might involve upgrades to an agreed level first. All mechanical treatment systems would be subject to maintenance contracts. The council would keep records of all maintenance certificates and contract reports.
Level 3: a utility operator takes over the monitoring and maintenance. A council may take on the maintenance programme and charge back the cost via rates or a direct charge. Alternatively, a private organisation (body corporate) could manage the O&M activity with reporting back to the council.
Level 4: the assets are actually vested in the agency, which manages them directly. This might be a council or a body corporate-type approach.
Clearly, with large lot sizes and low density of development, on-site systems are likely to have limited potential for creating environmental effects beyond the site boundary. Hence, the frequency and detail of monitoring inspections could be modified to accommodate the intensity of development and the likely performance of on-site systems.
Table 11.1 provides a model for the levels of inspection and procedures involved for various types of facility.
The previous discussion identifies some approaches to management options, which, if adopted, might mean that your community continues with on-site systems. How then do you balance this kind of management approach against other factors that might be pointing you to technical solutions? How can you be sure that it is a fixable management issue and not a technical problem?
First, you need to know:
In the end it may come down to a decision about how far your community's on-site systems have declined in quality, and how much it will cost to haul them back to an acceptable level.
Make sure you factor in information about how your community manages its on-site systems and match that with the scale of any problems and with the condition of the systems. Remember that there are a variety of choices, including continuing with well-managed on-site systems for parts of the community. (The choices are covered in Part Three.)
'Operations' usually applies to the day-to-day actions that need to take place to run a system. For example, to run a central wastewater treatment system, electricity is needed, as well as someone to monitor and oversee the system. These are operating costs.
In choosing an option the costs of operating any system need to be factored in. Interestingly, the operating costs of on-site systems tend not to be factored into decisions. Costs are generally absorbed directly by the homeowner or businessperson in terms of time and effort to monitor and look after the system. This is very misleading because it is the willingness of the owner to operate and maintain the system that is such a big factor in its long-term success.
At the very least, the time needed by an owner to run a system should be estimated and converted to some sort of hourly rate. If the community decides to commission external operations and maintenance, the costs will then be comparable.
For on-site systems, the operational issues are probably relatively small but will include monitoring and inspections.
The development of new technologies for monitoring on-site system treatment units and transferring monitoring data by phone lines to a central management and servicing agency now provides high-level, economical support to inspection programmes. Remote monitoring of a large number of systems on individual properties can be accommodated by computer data processing, with fault detection and alarm call-out procedures initiating maintenance responses to deal with emergency situations. Such monitoring technologies enable labour cost savings associated with operation and maintenance inspections (see Golden Valley subdivision example, Section 9.4).
This includes all the activities needed to keep the physical system at a high quality. Time and money spent on maintenance will extend the 'design life' of the asset and mean that you don't have to replace the system earlier than is needed. Maintenance can include routine cleaning of any pipes and screens, pump-outs of septic tanks, and associated testing. Monitoring of the physical state of a system will also be necessary.
Any system will have a life, beyond which it will be 'worn out'. It will need replacing at some stage and an important management concern will be to ensure that it is replaced at the best possible time. As much as possible, this needs to be right at the point where the system is still functioning well (so service levels are maintained) but just before it might fail. This involves expert judgement, and puts an onus on the homeowners to make that judgement, or to know when to seek expert advice. More often than not that advice is sought when the system fails. Commissioned management assistance may avoid this problem.
Building a new system, improving the quality of an existing system, or increasing its capacity may all be needed from time to time.
The management regimes for cluster and centralised servicing are well established, and may be administered by one of the following agencies:
The resources and procedures for operation and maintenance and monitoring of both the sewerage system and the treatment plant and ecosystem re-entry facilities will have been developed and refined over many years, with trained and experienced staff providing oversight of this full service approach.
In the case of a small subdivision in a rural area, sometimes a 'sewage package plant' is an acceptable solution to the local authority. This requires some form of legal agreement between the benefiting parties to provide for maintenance and management. This can be supplied under a turn-key contract and there are a number of suppliers of such systems operating in New Zealand. Speak with the New Zealand Water and Waste Association for an up-to-date list.
In urban communities a communal system of wastewater service is the most efficient and effective delivery mechanism. Typically in New Zealand the system has been provided and maintained by the local council, but in recent times arrangements have evolved to include other options, including:
Since the enactment of the Local Government Act 2002, franchising (in the Papakura form) is no longer an option and the general provisions relating to the ownership and operation of 'water services' by local authorities (water supply, sewerage treatment and disposal and stormwater drainage) are much more constrained.
Every territorial authority that provided water services at the commencement of the Act is required to maintain that capacity, the transfer of ownership or control to a person that is not a "council-controlled organisation" is prohibited, and contracts for the operation of water services cannot exceed 15 years.
The principal legislative requirements that have to be complied with are:
(For more information on the implications of the Local Government Act 2002, see Appendix 2.)
Whatever the system, be it public or private, it will have to be paid for somehow. This will include the:
For on-site systems, the owner will have to cover all costs, including capital, operating, monitoring and maintenance costs. Most owners of on-site systems make no provision for replacement costs, by setting aside money for depreciation of the asset. This would be like setting aside a sum each week to replace your washing machine when it wears out; the amount set aside would be an estimate of the replacement costs divided by the number of years of the life of the machine.
The following discussion deals with the funding of cluster or centralised wastewater systems managed by a body corporate, local authority trading enterprise, or council agency.
The capital cost of providing a proposed new system is of course very important but it is not as important as the cost that is going to have to be paid annually over subsequent years. In Appendix 6 some alternative systems arrangements are described with suggestions of possible ranges of capital costs. It may sometimes be better to select a system that is more expensive to build but cheaper to operate and maintain, than one that is cheaper initially but expensive to operate. However, the cost of loan servicing and the amount that is going to have to be put aside for depreciation are other important matters that will influence this decision.
In terms of a public system, there are three main ways of funding this capital cost.
The annual cost will be made up of direct maintenance and operating charges, loan interest and repayments, provision for depreciation, and, in the case of a council system, an amount for management and general overheads.
There are many ways these costs can be shared, and the first thing that needs to be done is to agree how much should be paid by the users and how much by the community at large. The answer to this question will vary from area to area, but normally the full cost (or almost all of it) will be required to be met by those whose properties are connected, or able to be connected, to the new system.
While rating according to the land, the capital or rateable value of properties is permitted, this is not often used for funding wastewater costs these days except in some rural districts where a targeted rate may be levied over an 'area of benefit'. The disadvantage of land-value rating is that the individual amounts charged often do not bear any resemblance to the use being made of the system, and this raises questions of funding equity.
Ideally, the method for collecting the annual charges should be one that encourages water conservation, but (except in certain industrial situations, where the tradewaste provisions mentioned later apply) in reality charging according to the quantity of water discharged is not legally allowed.
The most common method used is to levy charges 'per pan or urinal connected', subject to the provision that every separately occupied household is deemed to have only one pan. The charge may be uniform or according to a scale that reduces in price the greater the number of pans.
Another de facto user pays method is to levy a uniform annual charge per rating unit, or per separately rateable portion of every rating unit, that is able to be connected to the system. This option is particularly useful in the early years of the system's life, until the number of properties connected makes the pan charging approach viable.
It should be noted too that the availability of the system also benefits properties that are capable of being, but are not presently, connected, in that the ability to connect increases the value of the land. The usual practice is for the owners of non-connected properties to be required to pay a reduced fee usually 50% or 60% of the basic charge.
There have been long-running arguments about what schools should be required to pay. However, you should note that the former Rating Powers (Special Provision for Certain Rates for Education Establishments) Amendment Act 2001, commonly known as 'the Donnelly Act', now no longer applies and councils are free to decide what the charges for schools should be.
Ensure that tradewastes (wastes discharged from a trade premises in the course of any trade or industrial process or operation) are adequately controlled. In order to be able to levy tradewaste charges, a bylaw will be required. The usual approach is for the council to recover the reasonable costs for treating discharges of such strength and volume in excess of sewage of a domestic nature that would be discharged from a property of 'substantially similar rateable value'.
Ensure there is a process in place for requiring the payment of financial contributions to public wastewater systems by sub-dividers and developers. Before sub-dividers and developers can be required to contribute, unless the council is still able to use the provisions of the Local Government Act 1974 as a transitional measure it has to have an 'operative rule' in its district plan. Getting such a rule operative can be a long and difficult process. Another option in future is to use the new development contribution provisions in the new Local Government Act 2002.
Whatever the funding system proposed, if it is a local authority wastewater system there will have to be plenty of public discussion and consultation. The matter will have to be canvassed through the annual plan, and in future the proposed long-term council community plan. The provision of a new sewerage system is often very contentious, and anyone who makes a written submission about it has to be given the opportunity to be personally heard.
Another matter you may have to decide is how the proposed new system is to be accounted for in future. Often rural councils manage quite a few separate, relatively small schemes and there will be the question of whether there should be different charges for each or whether they should be managed and funded as one. Because of the impact of depreciation and of future capital renewal needs, the latter system has some distinct advantages.
A new and significant source of assistance for smaller communities is the Government's subsidy scheme for wastewater systems. It provides small and isolated communities with the ability to develop systems they might not otherwise be able to afford. The scheme is outlined below.
It is important to note that the assistance is for the capital costs of a project. If your community is considering the scheme, you need to make sure you have determined whether the operating, maintenance and replacement costs will be affordable. Note also that the subsidy is focused on off-site systems.
The following are the main criteria the Government has decided on for a Sanitary Works Subsidy Scheme (SWSS). The scheme is primarily aimed at improving sewage treatment and disposal for small, largely rural communities that are unable to fund the necessary upgrades to meet public health and RMA requirements. More detailed criteria will be developed prior to the scheme starting on 1 July 2003. Applications have been possible since 1 January 2003.
The main criteria are:
Any SWSS would not apply to:
Administrative arrangements will be developed around the following criteria.
For further information on the SWSS, please contact your local public health service.
In this case the property owner is the purchaser of the on-site system, and engages an engineer or a drainage contractor to:
The owner will have to engage O&M services, either through a maintenance contract or on a casual basis as demand requires. Where council maintenance certification schemes are in place to ensure sound operation and management practice across a locality or a district, owners will have to pay for the inspection and certification services as and when required under the terms of the council scheme. Where a body corporate structure is formed by a group of owners, such as in a ruralresidential subdivision, the body corporate will levy a uniform annual charge for operation and maintenance, and engage a servicing company to undertake the work.
Local councils have traditionally provided wastewater schemes through their works division or department. This can be via direct labour, or (more often) via council engagement of consultants to design the work, arrange tendering of the construction contract, and supervise the construction. The council processes the relevant planning and environmental consents; arranges funding via loans, or direct charges against budgeted capital works funds, and on completion of the work; and funds monitoring, inspection, and operation and maintenance services against its operational budget.
Two methods of purchasing wastewater schemes have been employed by some councils in recent years, although the Local Government Act 2002 may have made these alternatives less likely to be utilised. These are design-build-operate (DBO), and build-own-operate-transfer (BOOT) contracts.
In DBO the client, which may be a council or body corporate, engages a contractor to design and build the wastewater scheme and carry out the operation and maintenance for a defined period. The contract price includes purchase of all services leading to the construction of the scheme, and then operation and maintenance costs over the agreed period.
A BOOT project is a totally private venture in which the client pays annual fees to the BOOT company over a defined period, during which the company recoups its capital investment and operating costs. At the end of the defined period the BOOT company transfers ownership to the client, who then takes over responsibility for ongoing operation and maintenance costs. The advantage of BOOT to a council is they do not have to raise a loan to cover the capital costs. The BOOT company handles all financing.
BOOT contracts are more applicable for large projects, but DBO contracts are suitable for small community wastewater schemes. The Lake Hayes wastewater scheme undertaken by Queenstown Lakes District Council in 2002 is an example of DBO in action.
In December 2001 the Queenstown Lakes District Council (QLDC) tendered a 'design-build-operate' (DBO) contract for the Lake Hayes Water Supply and Sewage Disposal Scheme. The wastewater management component of the scheme included several kilometres of gravity sewer and four wastewater transfer pumping stations. The project required the contractor to:
The QLDC selected Transfund's 'Brookes Law' procedure as the tender evaluation method. This method is not common in DBO tender evaluations. Council believed this method provided the best selection method for the potentially difficult consent, easement and public consultation aspects of the project. In addition, the method allowed for the inclusion of high-quality engineering within the works an important consideration for a location such as Lake Hayes.
A joint venture between a civil engineering construction company and a consulting company was selected as the contractor with the highest attributes relating to experience, technical and management skills, and proposed methodology. The final contract price, including management, consultation, design and construction, and future operating costs, was negotiated within the council's budget, providing a win-win result for both parties.
The tendering method identified the contractor's attributes in a manner that allowed the council to select the best possible team to undertake the project. Construction was completed at the end of 2002.
19 Concepts are derived from the US Environmental Protection Agency model for requiring integrated decentralised wastewater management. return