Archived publication
This publication is no longer current or has been superseded.
This section provides guidance on all the inputs the model requires in order to generate the IBC. As noted in Section 4, the model can accommodate the development of new landfills (Greenfields) or the ongoing operation and possible extension of existing landfills (Brownfields). The inputs required for these two types of investments are broadly similar. The key difference is in the estimation of the initial capital expenditure (in the case of the Greenfields model) rather than the opening asset value (Brownfields model). Apart from this, the rest of the input parameters are similar for both models, and the guidance on the input is the same. Specific instructions relevant to the Brownfields approach can be found in sections 5.3.2 and 5.4.1.
It is important to note that for variables that require dollar value estimates, you will need to input the value in today's dollars, even if the variable requires an input in a future period. There is no need to account for inflation in providing these estimates. [Note, however, that over time the IBC will need to be adjusted to reflect inflation. See the discussion in Section 4.5.] The model automatically accounts for dollar value inputs being in today's dollars, and produces output in today's dollars.
A more detailed description of the costs not included in the FCA model is given in
Appendix C, but they can be summarised as follows.
The model is based on up to 11 information parameters and eight cost parameters relevant to landfill full cost accounting, as shown in Table 1. These parameters correspond to the item categories/headings in the model input worksheets (General Input,Brownfields Input, Waste Input, Geometric Input, and Cost Input), which provide the space for entering most data.
Table 1: Landfill parameters
| Model input worksheet | Parameter |
|---|---|
|
General input |
Situation - Section 5.3.1 Dates - Section 5.3.1 Waste - Section 5.3.1 Financial - Section 5.3.1 |
|
Brownfields input |
Existing conditions - Section 5.3.2 Works to be completed during residual life - Section 5.3.2 Stockpiles - Section 5.3.2 Financial - Section 5.3.2 |
|
Waste Input |
Waste - Section 5.3.1 |
|
Geometric input |
Site constants - Section 5.3.3 Development programme - Section 5.3.3 |
|
Cost input |
Sunk costs - Section 5.3.4 Planning and pre-development - Section 5.3.4 Base costs - Section 5.3.4 Development - Section 5.3.4 Operation - Section 5.3.4 Closure - Section 5.3.4 Aftercare - Section 5.3.4 Contingencies - Section 5.3.4 |
The general input data include the following.
The Brownfields input data include the following.
The geometric input data include the following.
The cost input data include the following.
The following sub-sections provide guidance on some of the items. Indicative values or costs (range, typical and default costs or values) for items are provided in Appendix B by way of guidance.
You are strongly advised, before you take the results of this model beyond the initial drafting stage, to obtain advice on these inputs. The rates provided are for guidance only and are likely to alter according to relevant market and economic factors as well as site-specific data.
The sources - and therefore the accuracy - of costing information will depend on whether the site is an existing and operating landfill or a planned site, and the degree to which planning, resource consent processes and design have progressed.
Information sources will include:
The Brownfields model requires an input related to the opening asset value of the existing landfill. This value should be as per Financial Reporting Standard 3 (FRS-3) or NZIV [NZ Institute of Valuers. These guidelines are broadly consistent with FRS-3.] guidelines. You should consult your accountant(s) or specialised financial advisers to ensure that the value you input here is consistent with these standards and guidelines.
Only the costs that can be attributed directly to the site finally chosen should be included as initial/sunk costs in the FCA model. Typically these would include site selection (directly related to the proposed site), planning and site investigations.
This covers all costs for management, administration and organisation overheads associated with the landfill during the pre-development phase of the project, including:
Only the costs of research and investigations that can be attributed directly to the site finally chosen can be included in the model. Sources of information on the costs of landfill site selection include:
The costs of consultation are specific to the project and should include public consultation (meetings, information bulletins, media releases, etc) as well as consultation with interested and affected parties. Sources of information on the costs of the consultation include:
The costs of survey and preliminary design, geotechnical and groundwater studies and other detailed investigations or studies (noise, traffic, visual, etc.) depend on the scale and significance of the project as well as the specific attributes of the site. Sources of information on the costs of site proving include:
A preliminary site assessment and discussions with the regional council as well as specialist advise from consultants can provide a guide to baseline monitoring requirements and associated costs.
As with the site selection process, the resource consent process can be long and involve substantial cost. The time and cost can be expected to be greater for a new site than for an existing site. The resource consent process requires the following:
In the model the resource consent item covers:
Sources of information on the costs of the resource consent process include:
Land cost covers the cost of all land purchased and used for the landfill. It includes the cost of any land bought for leachate and/or stormwater treatment, access roading and buffer areas, legal costs, and the cost of negotiations associated with land purchase.
In some cases land may be leased for any of the above activities. Here it is important to ensure that any financial costs associated with the lease are reflected in the discount rate and not in the operating costs. This will avoid any risk of double counting such costs. Generalised guidelines cannot be provided in these cases and specialist input should be obtained.
Current landfill siting and design requirements mean that the types and locations of land appropriate for development as a landfill in a district are limited. For new landfill sites the cost of land may be significantly higher than the value of the land under its existing use. This is a reflection of the market demand due to limited availability of appropriate land and the likelihood that the land is more valuable to a council, or community, as a landfill than in some alternative use.
The base costs of engineering (detailed design and documentation, and construction management) and contractor's preliminary and general (P&G) associated with landfill development are included.
All intersection upgrades, other roading network upgrades/contributions, access road to the landfill footprint, and special structures (diversions, bridges, etc.) required to cater for increased traffic or increased vehicle loads due exclusively to the landfill should be included.
This item covers:
This covers all costs associated with the installation of groundwater collection drains and discharge of groundwater from beneath the site.
This covers all costs associated with bulk earthworks for site preparation, including the costs of removing or importing material.
This covers all costs associated with purchase of liner materials, liner protection materials (including temporary protection), liner construction and additional site preparation required prior to the placement of liner materials. Also included are costs associated with testing liner materials and quality assurance/quality control procedures employed during liner construction.
The geometric and cost inputs for liner construction allow for the use of up to 6 different liner types. Each liner type can incorporate subgrade preparation, low permeability material (i.e. clay), synthetic liner (i.e. FML and/or GCL), a liner protection layer, and a leachate collection layer.
In many cases, a single liner type will be suitable for the whole landfill, however in some cases, differing liner types may be required such as where the sidewall liner type differs from the base or floor liner type. The difference may be as small as omission of, or reduction in, the thickness or material type of one layer in the proposed liner.
Each cell can use any combination of liner types, however the default is Liner Type 1. All residual footprint area not allocated to another liner type is allocated to Liner Type 1.
Apart from the low permeability material, all layers are costed per square metre. Therefore the unit rate costs entered in the Cost Input sheet for each layer must be calculated to take account of any relevant thickness variations. Any layer which is not required for a given liner type should have its cost deleted (or set to $0) in the Cost Input sheet. Where low permeability material is not required for a particular liner type, its thickness should be set to zero in the Geometric Input sheet.
All geometric inputs are based on plan areas and not projected areas. Where slopes are particularly steep, some adjustment to the liner costs may be necessary to allow for the difference between the plan and projected areas.
At the initial project planning stage the type of liner may be unknown, and hence for this case the user should only input values for a default liner (Type 1).
The default liner suggested is the United States Environmental Protection Agency (USEPA) Subtitle D liner: a composite liner consisting of two components. The upper component must consist of a minimum 0.75mm (30 mil) flexible membrane liner (FML), and the lower component must consist of at least a 600 mm layer of compacted soil (clay) with a hydraulic conductivity of no more than 1 x 10-9 m/s. Under Subtitle D, FML components consisting of high density polyethylene (HDPE) must be at least 1.5 mm (60 mil) thick. It should be noted that the model does not automatically calculate or allow for a Subtitle D liner.
This covers all costs associated with the development of the system, including pipes, sumps, cleanout ports, manholes, automated pump station (pumps, valves, fittings and electrical) and collection layer.
This covers all costs associated with the development of the leachate pre-treatment / treatment and/or disposal system, including:
The costs of the system may vary considerably depending on the method of treatment and disposal and the quantity and quality of leachate. The model provides the flexibility to include all treatment and disposal options, including short-, medium- and long-term methods of leachate management to deal with changes in leachate quality and quantity over the life of the facility.
This item covers all costs associated with the construction of major stormwater diversion (for example, dams and canals), open drains, stabilised drains / flumes, piped drains, and stormwater treatment (ponds and instrumentation).
This item includes the installation of any landfill gas collection and monitoring bores, pipework, treatment systems, vents, flares and sampling points, both in and around the site.
For existing sites this item should include the cost of property purchase or installation of gas cut-off trenches and barriers to reduce gas hazards in the vicinity of the landfill site when these actions are required.
This includes the cost of all cover material, revegetation and any placement of final cover and revegetation not accounted for in the daily operations budget or operations contract.
The placement of daily cover and intermediate cover is accounted for in the landfill operations.
This item covers either the contract for day-to-day landfilling operations at the site, or the costs of site staff and plant operation. In some cases it may be a combination of the two. Included are all the day-to-day operations undertaken by the contractor or site staff, such as:
Where a landfill is a component of a larger waste management system, administration and overhead costs related to the landfill should be separated out and charged directly to the landfill.
This item covers the cost of environmental and other monitoring not carried out by staff on site, along with associated expert advice, interpretation, record keeping and reporting, and external costs. The types of monitoring to be accounted for are:
This item includes the cost of installing monitoring facilities such as groundwater monitoring bores, surface water weirs and landfill gas monitoring bores during the operating life of the landfill. It also includes the purchase of specialist monitoring equipment, if required.
Host fees, where applicable, are payments made to the local community affected by a landfill for appropriate community projects (for example, a community hall). They can take the form of lump sum grants or an amount per tonne of refuse accepted at the site, or a combination of the two, for the development and/or maintenance of community facilities. The value of host fees may be calculated during the resource consent process.
The Landfill Guidelines (Centre for Advanced Engineering, 2000) state that the minimum time period for aftercare of a landfill is around 30 years. The full cost accounting process for a landfill includes all costs associated with the post-closure rehabilitation and aftercare of a site until such time as the appropriate regulatory authorities determine that it has no significant potential for adverse effects on the environment.
Regulatory authorities generally require the preparation of a closure and aftercare plan prior to completion of landfilling at a site.
If the landfill user charges are derived from the full cost analysis and reflect the costs of aftercare, then this proportion of the landfill income will not be spent until after the site is closed and (possibly) available for other uses.
For existing or new landfills, the opportunity exists to levy each tonne of solid waste disposed at the facility via the tipping fee as a disposal cost levy (section 542 of the Local Government Act) to provide the funds for these costs. Another method is to pay the costs of closure and post-closure using rates or taxes collected from the relevant community, or a combination of rates, taxes and disposal cost levy. If financial assurance for meeting future costs has not been implemented during the operational life of the now-closed facility, the costs of closure and post-closure will probably have to be met by the community in the form of rates and taxes.
The impact of the decisions made in the first three stages of the project (see 'Different WACCs for different Greenfields stages', section 5.4.21) on the environment will be felt in this final stage as the site is restored to a useable state. There is considerable uncertainty over the rehabilitation liability taken on by a landfill operator once the landfill is closed, and also over quantifying the cost involved in the clean-up and rehabilitation phase of the project. Also, the estimated time frame for the rehabilitation and clean-up stage (15-30 years beyond the closure date of the landfill) of the project is fairly uncertain, with the highest projected monitoring period as long as 35 years after closure. This estimate is dependent on the location of the site selected (for example, drier terrain will increase the time required for the waste to decompose, and vice versa).
The methane gas produced by the landfill may be able to be used to incinerate the leachate and produce electricity, which would result in a reduction in the cost of stage 4. This option is dependent on where the landfill is situated (near a power station or population) and the amount of capital expenditure required. If this possibility were to be factored into the cashflows for stage 4 and then did not occur, for technical or economic reasons, unexpected stage 4 costs would result. This adds to the uncertainty surrounding the cost that will be incurred during this phase and the level of risk.
As a result, this post-closure exposure period is best characterised as one of low expected costs, ideally covered by amounts calculated and funded during the operating period. At the start of the project evaluation an estimate will be made of the closure and aftercare costs. The sum of these must be accumulated during the operation of the landfill taking into account current deposit rates. The model will need to reflect the accumulation of the 'sinking fund' when calculating the gate price per unit.
While there are some closure activities that are common to all landfill sites, others are site-specific and/or resource consent-specific. Typical closure activities include:
It is important to reiterate that actual costs will be site-specific and may vary significantly from those presented in Appendix B. The reader is also referred to A Guide to the Management of Closing and Closed Landfills in New Zealand (Ministry for the Environment, 2001b).
Closure and post-closure cost estimates are best developed using actual costs from current landfill operations, as well as historical costs from closure and post-closure activities. Changes over time are likely to occur in the estimates due to increasing regulatory requirements and/or new technologies. The following major components of post-closure may be expected to decrease over time.
Key financial considerations for closure and post-closure are as follows.
Contingency costs associated with the pre-development, development and operation, closure and aftercare of the landfill should be included. Typically figures of between 5% and 25% are used, depending on the level of accuracy of the costs of the individual items in the analysis.
The cost of capital is defined as the return investors in a firm or project expect to earn given the degree of risk associated with that firm or project. It represents the opportunity cost of investing in an asset with risk comparable to the asset being evaluated. For example, a relatively risky venture, such as investing in oil exploration, has a higher cost of capital than investing in a utility company.
Cost of capital can then be used to 'discount' the cashflows of projects or businesses as investors are forgoing the opportunity in the intervening period. When used in this way future cash flows are converted to a 'present value', expressed in today's dollars (a key component of the landfill model). Essentially, this discount factor accounts for both the 'time value of money' (a dollar today is worth more than a dollar in the future) and the riskiness of a project or business.
The commonly accepted cost of capital is the weighted average cost of capital, or WACC. The calculation of WACC is a relatively complex task and you should seek specialised advice from either your accountant(s) or external sources before calculating the required input. WACC is not directly equal to debt cost.
The formula below broadly outlines the approach that should be followed in order to calculate the WACC input for the model:
![]()
Where:
Debt = market value of debt
Equity = market value of equity
Cost of Debt = pre-tax return required by debtholders
Cost of Equity = pre-tax return that shareholders expect.
In short, WACC is a weighted average of the returns expected by debtholders and equity or shareholders for investing in an asset such as a landfill.
The cost of equity, or the risk-adjusted return required by shareholders, is not directly observable, but can be estimated using the capital asset pricing model (CAPM). This estimate is made as follows:

Where:
Risk free interest rate = the interest rate of risk free security
Market risk premium = the premium that the market returns over and above the risk free rate
"Beta" of Equity = the sensitivity of the returns of a firm's shares to fluctuations in market returns.
An important point to note in the context of both forms of this landfill model [Greenfields and Brownfields.] is that the WACCs used need to be estimated in pre-taxand real [As distinct from nominal, or including the effects of inflation.] terms. This is because there needs to be consistency between the cashflows being discounted and the discount rate being applied. As the cashflows being discounted are before tax and 'real' (they are not adjusted for inflation), the discount factor or WACC must be consistent with this and so should be reflected in pre-tax real terms. Again, because of the complexity of this issue, you should seek specialised advice from either your accountant(s) or external sources before deciding on the appropriate discount rate.
A Greenfields landfill project can be divided into four specific stages based on the types of risks that an operator will be exposed to during its life. These stages are outlined below.
Examples of the level of WACC risk rating that each different stage would attract are indicated below. The differing discount rates will reflect the quite different risks faced in each phase of a landfill project. For example, typically the site selection phase is inherently more risky than the operation phase because of the relatively greater risks inherent in finding suitable sites.
Table 2: Examples of WACC ratings at different stages of a landfill
| Stage 1 | Stage 2 | Stage 3 | Stage 4 | |
|---|---|---|---|---|
Project stages | Planning and pre-development | Development | Operating | Aftercare |
WACC risk rating | Venture capital | Building company | Operating company | Operating company |
Note that in the case of a Brownfields landfill, only one WACC is required - relating to that of a landfill operating company. From stage 3, the risks are representative of the business risks of the landfill.
As you may note the model already has data in the Cost of Capital data entry cells. These values are as follows.
Table 3: WACC for different stages of landfill development
| WACC* | |
|---|---|
Planning and pre-development | 25% |
Development | 25% |
Operating | 10% |
Aftercare | 10% |
* This should be expressed in real, pre-tax terms.
However, note that these default values are inserted only to enable the model to generate an IBC value.
Before taking the results of this model beyond an initial drafting stage, you are strongly advised to obtain advice on these inputs. These rates are likely to alter depending on relevant market and economic parameters.