Table 2: Indicative cost/benefits of case study office buildings

Return to the point in the document where this table is located.

 

Building type

Benchmark building capital cost
$/m2

ESD building capital cost
$/m2

ESD building premium (saving)
$/m2

ESD building premium (saving)
%

Annual energy cost savings
$/m2

Annual water cost savings
$/m2

Total annual cost savings
$/m2

Simple payback
(years)

20-year NPV for ESD measures
$/m2

Office - low/ medium ESD

2000

2130

120

6.0

11.0

0.3

11.3

10.65

-3

Office - medium/ high ESD

2000

2230

230

11.5

17.0

0.6

17.6

13.09

-23

 

 