|
Client |
Waitemata District Health Board |
|---|---|
|
Site address |
Lincoln Road, Henderson, Auckland |
|
Total floor area |
14,700m2 |
|
Cost/m2 |
$2435 (adjusted to 2005) |
|
Conventional cost/m2 |
$2400 (1.5% below project cost) |
|
Contract value |
$35 million |
The indicative economics for this case study building are set out in the table below. Adding sustainable building strategies was initially seen as too expensive, but a subsequent feasibility study and loan funded by the Energy Efficiency and Conservation Authority (EECA) under its design energy audit and Crown loan scheme proved otherwise. A grant was also received from Infrastructure Auckland for the stormwater measures included in the project (not accounted for in the table below).
View the indicative economics for this case study building (large table).
Due to their intensive use and highly serviced nature, hospitals can be excellent examples of sustainable building.
Site:
Material:
Waste:
The Waitemata District Health Board and Waitakere City Council worked in partnership with the community to ensure that the hospital fitted with Waitakere City's Eco City vision.
The two-level hospital block comprises:
The site development included partial refurbishment of existing buildings and the construction of new facilities. Courtyards were created in the middle of the building to bring sun, light and air into the interior and provide green space for the occupants. A landscaped stormwater retention and treatment pond provides a public amenity for the site.
As part of the project development, a series of design principles was created, underpinning the design direction. These included:

Energy-savings options were modelled and tested to identify their cost benefits. The first was for the partial recirculation of air using an economiser cycle. This improves the efficiency of the system by using outside air for cooling when conditions permit.
High-efficiency lighting was used, which included:
The levels of insulation were increased from code levels, with R 2.0 insulation in the walls and R 3.5 in the ceiling. Natural ventilation was provided to the assessment, treatment and rehabilitation (AT&R) wards and to cultural health.The pump and fan energy use has been reduced by the use of low-pressure loss systems and high-efficiency motors.The building management system (BMS) controls all systems serving the hospital in an energy-efficient way, based on time of day, outside weather conditions, internal conditions and the presence of people. It also provides an energy management tool to ensure energy use can be monitored.The table below shows the economics for the energy savings measures that formed the basis of the Crown loan application. Taking into account the capital costs saving for adopting natural ventilation, the capital cost premium fell to $50,000 and the payback period to 0.33 years.
View energy saving measures (large table).
Hospital foyer
Stormwater from the hospital flows into a landscaped stormwater pond before flowing into nearby Henderson Creek. The car park stormwater flows into swales and rain gardens and then flows into the same creek. This cleanses the water of sediment and pollutants and also prevents flooding downstream.
Swales: Stormwater from the new car park and access road at the back of the hospital site runs off into the swales. About 450m of lineal swales were installed to cope with approximately 3400m2 (30% of the paved area on the site) of road area.
Two sand filters: These have been fitted next to the new main car park to help treat the existing 300 car park spaces.Rain gardens: Installed at the end of the swales, these naturally filter run-off from the car parks before the water enters the stormwater system. Stormwater treatment pond: This 1900m2 pond treats the stormwater to 75% efficiency. It treats stormwater from an 18 ha catchment area. Rainwater tanks: Six 250m3 tanks collect rainwater run-off from the main hospital roof, with the water used mainly for toilet flushing and cooling tower make-up. Estimated savings from reusing this water equate to annual water consumptions bills being reduced by $15,000 per annum, a significant saving given that during 2005 water costs in Auckland increased from $1/m3 to $4.50/m3.
On-site green tanks
Wherever possible, existing hospital elements have been re-used, upgraded and integrated in the new community hospital, with about 50% of the hospital being retained and progressively upgraded.
No formal system of waste management was established, but the contractor was well organised and minimised the amount of prefabrication, re-work and waste disposal.
The hospital is moving towards establishing a formal waste management system like the one being implemented by Wellington Hospital. Clinical waste costs about 25 times more to dispose of than general waste - and up to 75% of the materials disposed of as clinical waste are actually general waste. The waste management system will include:
As identified at Wellington Hospital, quick gains can be made by addressing specific items such as gloves, IV bags and nappies.
Existing buildings were re-used and refurbished. Stormwater retention and treatment ponds serve as a public amenity. Swales and rain gardens are used to deal with run-off from car parks.
Public access has been improved and made easier with a barrier-free philosophy.
Waitakere residents previously had to travel to the North Shore for accident and emergency facilities. The new hospital in West Auckland reduces car trips significantly. A new traffic light interchange at the hospital entry improves traffic flows and safety.
The choice of materials and their environmental effects were considered, but the lack of a direct return on investment and higher cost made uptake limited. Some specific measures showing a positive return on investment were adopted.
A master plan was first developed by the hospital general manager, with the hospital's Orion Programme management team, Di Carlo Potts Architects, project managers Carson Group, quantity surveyors Rider Hunt and Maunsell Consultants. Hospital staff then put together a brief for each department and a business plan was put to the government. Other consultants were brought into the process, including services engineers and energy modellers Connell Mott MacDonald, civil engineer Harrison Grierson and structural engineer Buller George. An advisory group including Waitakere City Council, the Energy Efficiency and Conservation Authority (EECA) and Robert Vale from Uniservices stimulated interest in the development of an 'Eco Hospital'. A cost/benefit analysis of energy and water savings, funded by EECA's Design Audit Scheme, was carried out by Connell Mott MacDonald. This justified contributions and loans from EECA and Infrastructure Auckland, and meant the project was the first to benefit from EECA funding for both a design audit and Crown Loan.
Unfortunately, with no detailed design brief available at the start of the design process, no clear objectives were set for energy saving and no benchmarks were made. This will make judging the success of the energy-efficient design very difficult. Robert Vale (a sustainable building consultant on the design team) recommends the following process for future projects:
Client: Waitemata District Health Board
Project manager: Carson Group
Architects: Di Carlo Potts Architects (Sydney)
Quantity surveyors: Rider Hunt
Services engineers and energy consultant: Connel Mott MacDonald
Civil engineer: Harrison Grierson
Structural engineer: Buller George
Sustainable design consultant: Robert Vale, Waitakere City Council Sustainable Design Advisor