
| Client |
Christchurch City Council |
|---|---|
| Site address |
Cnr Colombo Street and Hunter Terrace, Beckenham, Christchurch |
| Total floor area |
2400m2 |
| Cost/m2 |
$2494 (2005, including park, landscaping and roading) |
| Conventional cost/m2 |
$2384 (4.9% below project cost) |
| Contract value |
$4.6 m including park, landscaping and new road |
The indicative economics for this case study building are set out in the table below. Note that water saving measures do not show any payback due to the method of charging water in Christchurch. However, this situation is likely to change in the future as water supplies come under increasing pressure.
Incorporating a considerable number of environmentally preferable materials and technologies in the building also has no direct payback but was accomplished for less than 1% of the total construction costs. Taking these factors into account, along with the fact that this type of building is less intensively serviced, makes this type of sustainable building a medium to long-term investment - normally acceptable to a local authority client.
View the indicative economics for this case study building (large table).
Energy use:
Water use:
Stormwater design:
Site:
Material:
Waste:
The client brief was to provide a library building that would give a much needed focus for the lower Cashmere Community in Christchurch. The building design was developed through an extensive community consultation process.
It was to be sympathetic to the residential character of the area while at the same time maintaining a civic presence. A key component of the brief was also to meet the Council's policies on environmental sustainability and energy use.
The building houses three key functions: a community library, an education centre, and the local council service centre and advocacy team. It also provides a number of other community facilities such as formal and informal meeting rooms, a display space, a café and offices for the community constable.
The site was council-owned. It had an existing building, with the rest of the site fenced off for use by the Christchurch City Council water services department.
There was a significant number of mature trees and vegetation as well as hardstand areas, several aquifier water supply wells, pump stations and other ancillary facilities. To the north, the site was bounded by Hunter Terrace and the Heathcote River.
A low-rise single-storey building in keeping with the residential nature of the site, it uses a dramatic saw-tooth form and a stepped plan sitting in a water-filled moat to create a distinctive presence.
The site was cleared of buildings, and the mature vegetation retained and tidied to create a public park for the community. In time, part of Hunter Terrace to the north of the park will be closed off and the park will spread down to the edge of the river.
The building is solid and heavily insulated to the south where back-of-house facilities are located, and gradually opens up to the park in the north. Visitors enter the building from the south and are led across to the public spaces in the north which look out onto the landscape.
The saw-tooth roof form breaks the building into four distinct blocks and allows daylight and ventilation to penetrate deep into the plan.
The passive low-energy concept design focused on the following:
These passive strategies were overlaid with the following active strategies to further minimise energy use:
In all cases, low-energy design solutions were rigorously tested through 3D energy modelling to ensure they met the client's payback criteria, which was five years for equipment, but longer for fabric changes such as double glazing and insulation.
Water conservation was not a high priority, however a number of innovative techniques were employed to reduce water use and minimise the volume of sewage leaving the site. Low-water-use plumbing fittings were specified throughout, including:
The water-filled moat around the building is also used as a collection and holding tank for rainwater supply for the toilet cisterns.
Waste minimisation was an issue of key importance to the client:
Within budget constraints, the designers sought to select environmentally preferable materials, including:
The site design is an integral part of the ecological design.
The building has a large 70-space car park that is often full. However, the client tries to reduce vehicle use by:
Key changes to the normal procurement process were pivotal to the environmental success of the project:
Since its opening, the facility has been hugely successful, with the informal character and café attracting more visitors than anticipated. The building is also well liked by the staff and - because of this - some of the more unusual features seem to be well understood and managed.
However, it remains to be seen whether or not the building will continue to be managed as well when the novelty wears off.
Engineers took significant time and effort during commissioning and monitoring energy uses. This commissioning continues and the engineers are confident that further energy savings will be achieved.
The water-filled moat caused particular problems during commissioning. Algae build-up was not controlled sufficiently by the proposed enzyme treatment and filtration system. The actual effect of the moat on overall water use is not known because water must be topped to cope with evaporation losses.
The moat has been designed with a river boulder base to look like a dry riverbed in droughts. This facility has yet to be used and does create some additional cleaning requirements. However, the moat is a successful architectural feature and the security it provides means the building can have opening windows and doors.
Client Christchurch City Council
Project manager City Solutions
Architects Warren and Mahoney
Quantity surveyors Shipston Davies
Contractor Mainzeal
Landscape architect City Solutions
Structural and civil engineers City Solutions
Electrical engineer Beca Carter Hollings & Ferner Ltd
Mechanical and fire engineers Beca Carter Hollings & Ferner Ltd