| Activity number |
Activity description |
Commissioning agent (CA) |
Building services contractor (BSC) |
Builder (B) |
Design engineer (DE) |
|---|---|---|---|---|---|
1 |
Review DE’s design drawings and specifications for commissioning requirements. |
Action and advise DE. Co-ordinate any comments from BSC and B. |
Review comments and action as appropriate. |
||
2 |
Review installation drawings and technical submissions from BSC for commissioning requirements. |
Action and advise B and DE. |
Prepare and submit for review. Action any comments as instructed by B. |
Co-ordinate, supervise and direct/instruct as appropriate. |
Review, comment and issue directives to B if applicable. |
3 |
Review installations with respect to compliance with specifications and drawing intent for commissioning |
Supervise inspection of installations and issue reports to B and DE. |
Receive CA reports and action as necessary. |
Co-ordinate, supervise and direct/instruct as appropriate |
Review, comment and issue directives to B if applicable. |
4 |
Produce detailed co-ordinated commissioning plan, including revisions and updating. |
Procure information from BSC. Prepare programme, discuss with B and issue to all parties for comment. |
Submit plans/ information and liaise with CA. |
Review programme with regard to its impact on the construction process. Issue comments and approve. |
Review, comment and accept. |
5 |
Produce detailed commissioning method statements, including pre-commissioning, setting-to-work and interface tests. |
Guide and assist in their production. Review and accept content. Liaise with B and DE. |
Discuss format and content with CA. Produce method statements. |
Receive, review and approve. Liaise with DE and CA. |
Review, comment and accept. |
6 |
Testing and pre-commissioning, including off-site works testing (as requested). |
Procure procedures from BSC and suppliers for approval. Witness and validate tests and results. |
Submit information and liaise with CA. Complete outstanding works schedules. |
Review/comment and approve. Carry out spot checks. |
Review, comment and accept. Carry out spot check as required. |
7 |
Produce project-specific test sheets. |
Prepare and issue pro forma sheets, including interface and performance tests. |
Liaise with CA. |
Receive, review and approve. |
Review, comment and accept. |
8 |
Monitor and report on commissioning progress. |
Prepare spreadsheets to be used to monitor all progress. Issue and update at regular intervals. |
Assist CA during monitoring process. |
Receive and review reports and circulate. Monitor progress and manage any programme changes. |
Review and comment. |
9 |
Progressive installation tests and pre-commission. |
Monitor, witness and ensure accurate recording of all results, in accordance with method statements. |
Implement testing. Prepare records and demonstrate. |
Monitor progress. Carry out spot checks. |
Review, comment and accept. Carry out spot checks as required. |
10 |
Pipe-work system flushing, cleaning and dosing. |
Monitor, witness and ensure accurate recording of all results, in accordance with method statements. |
Implement activities, prepare records and issue analysis reports. |
Monitor progress. Carry out spot checks. |
Review, comment and accept. Carry out spot checks as required. |
11 |
Setting-to-work of plant and systems, commissioning and performance testing in accordance with programme. |
Direct BSC, giving guidance as necessary. Witness activities and ensure accurate recording of results. |
Execute all planned activities. Demonstrate selected items to B/DE as directed. |
Monitor progress. Witness as required. |
Carry out spot checks and witness activities on a selective basis. |
12 |
Prepare testing and commissioning reports, incorporating all plant and system test results. |
Action and submit to B. |
Liaise with B and supply all relevant documentation. Action adjustments to system performance as advised or instructed by B. |
Monitor progress. Issue directives/instructions to BSC as appropriate. |
Review, comment and accept. Issue directives to B as appropriate. |
13 |
Prepare models for record documents/drawings and O&M manual format. |
Monitor preparation, and comment on submissions via B. |
Submit information and liaise with CA. |
Monitor progress. Liaise with client. Issue directives to BSC, as appropriate. |
Review, comment and accept. |
14 |
Provide demonstrations to the relevant territorial authorities. |
Manage and co-ordinate the demonstration of all life safety systems, as required, to the statutory authorities. |
Execute all planned activities in conjunction with the B. |
Monitor progress. Attend demonstrations. |
Review, comment and attend demonstrations. |
15 |
Prepare final record documents |
Receive, collate and comment on submissions by BSC. |
Submit record documents for approval and liaise with B. Update to suit comments. |
Issue to client and co-ordinate all comments with BSC. |
Review, comment and accept. |
16 |
Client/end-user awareness and liaison |
Co-ordinate activities and advise the client of all potential operational implications. |
Liaise with CA and be responsive to the client/end-user’s needs. |
Liaise with the client/end-user. |
Monitor status. |
17 |
Client/end-user training programme. |
Co-ordinate and manage BSC contractual obligations. |
Liaise with CA. Co-ordinate the activities of specialist suppliers. |
Monitor progress and participate. Liaise with client/end-user. |
Review, comment and accept. Participate as required. |
18 |
Post-occupancy fine-tuning/warranty period |
Review operation with facilities management staff, initially on a monthly basis for the first three months and then quarterly. |
Carry out post-handover fine-tuning, respond to any operational problems and attend to any required remedial works. |
Assist in directing any BSC remedial work and attend to any building remedial work. |
Respond to any design-related issues raised during the post-occupancy period and carry out warranty inspections. |
19 |
Post-occupancy warranty period energy/water-use monitoring |
Review energy- and water-use trends with facilities management staff and refer issues to DE or BSC, as appropriate. |
Attend to any remedial works requirements. |
Assist in directing any BSC remedial works. |
Attend to any remedial design action required. |