IWBDP project checklist

This checklist provides an overview of the principal activities involved in the integrated whole building design process.

Activity Complete
 

Small building (≤500m2)

Medium building (>500m2 ≤1000m2)

Large building (>1000m2)

  1. Require adoption of IWBDP and recommend adoption of NZCIC Design Documentation Guidelines by the project team (refer to Further reading section).
     
  1. Appoint an IWBDP facilitator or champion.

N/A

   
  1. Carry out a visioning workshop and stakeholder consultation.
     
  1. Summarise the project goals identified in the workshops and consultations into the outline building brief and issue to the design team as the basis for design.

N/A

   
  1. Carry out concept and preliminary high-level design workshops and write reports.

N/A

   
  1. Carry out targeted elemental developed design workshops and write a report.

N/A

   
  1. Specify that the design team uses Building Information Modelling (BIM) for detailed design documentation.

N/A

   
  1. Arrange for the independent commissioning agent and facilities manager to review the design for buildability, maintainability, and commissioning.

N/A

   
  1. Provide building user guide training and facilities management training.

N/A

   
  1. Arrange for an independent commissioning agent to oversee and report on building commissioning.

N/A

   
  1. Ensure building maintenance contracts are set up during the first six months of operation.
     
  1. Ensure first-year building fine-tuning is carried out and provide feedback to the design team.

N/A

   
  1. Carry out operational energy, water and waste auditing and provide feedback to the design team.
     
  1. Carry out post-occupancy evaluation of the building after nine months of operation and provide feedback to the design team.
     
  1. Carry out triennial building audits.
     
  1. Allow for any continuous commissioning as a result of triennial audits.

N/A

   
  1. Include a green performance schedule if building is leased.

N/A

   

 

[ |