To better understand the challenges faced with large resource consent applications, the Ministry for the Environment commissioned a review of resource consent applications made by TrustPower Limited to construct and operate a new hydro power scheme on the Wairau River, Marlborough. This report presents the findings of this review as learnings for future large resource consent applications.
The Ministry for the Environment (MfE) has commissioned a review of the processing of resource consent applications made by TrustPower Limited (TPL) to construct and operate a new hydro power scheme on the Wairau River, Marlborough. The applications were processed under the provisions of the Resource Management Act 1991 (RMA) by the Marlborough District Council (MDC), which is a unitary authority under the Local Government Act 2002. The sole focus of the review is on the process employed by MDC to progress these consent applications, not the merit of the subsequent decisions made.
The first step in the review was to scan all the relevant MDC files on the applications, and speak to a number of relevant MDC staff. Two staff members of TPL were then interviewed, followed by interviews with representatives of six submitters, all of whom opposed the applications. These representatives were chosen because of their experience with statutory processes under the RMA.
Some of the criticisms made by these respondents were then put to the MDC for their response, and each of the three hearing commissioners were interviewed separately. This completed the gathering of information for the review.
The applications were lodged in July 2005 and notified in September 2005. The submission period was doubled to 40 days with the agreement of the applicant. There were 1442 submissions on the applications - 1117 were from within the scheme area; 325 from beyond. Five hundred and twenty-seven submitters supported the application, of which 80 wished to be heard. Nine hundred and three submitters opposed the applications, of which 527 said they wanted to be heard.
The applications engendered some strong feelings in the local community, most of them opposed to the proposed power scheme.
In November 2005, the MDC appointed a hearing panel comprising Tony Willy, a former judge who had served on the District Court, Tax Court and Environment Court as chair; Max Barber, an experienced resource management consultant; and Jill Bunting, a second term district councillor and then chair of the council’s hearing committee.
The hearing, which commenced on 12 June 2006, was adjourned on 12 December 2006 after 70 hearing days. An interim decision was released on 22 June 2007. The interim decision granted the applications sought by TPL, but did not specify the conditions on which they were granted. The “conditions hearing” took eight days between 12 January 2007 and 12 February 2007. Decisions on the conditions were released on 5 August 2008.
The interim decision was appealed by six parties, two of whom are closely linked. Those appeals have yet to be heard. One appeal – that from the Department of Conservation – has provisionally been settled with TrustPower.
The MDC contracted a local consultant and former council employee to help process the applications.
Submitters interviewed about the consents process made favourable comments about some elements of the processing of the TPL applications by MDC including:
However, there were some strong criticisms raised by submitters interviewed concerning the hearing of the applications. These included:
The hearing panel split its decision and decision making into two parts. This followed a meeting with the applicant and the main institutional submitters1, all of whom agreed to this approach. The first decision was to grant the consents sought, but without conditions.2 This decision subsequently gave rise to six appeals (two of which are closely linked) being lodged with the Environment Court. A separate hearing on conditions followed, with decisions being released some 13 months after the primary decision. TPL lodged an appeal to some of the conditions of consent.
All the submitters interviewed were critical of this two step process. In particular, they said that the conditions form part of the mitigation package on which consents could be granted, and this had to be a key component of the decision. They also noted that this process added substantially to the time involved in decision making. Some submitters expressed frustration that they could not speak to conditions at the original hearing, as they had originally prepared evidence on this basis.
Members of the hearing panel had a different perspective. They considered that right from the start of the process there was a significant possibility that the applications would be declined, particularly as some were for non-complying activities. Given this, they believed the most expedient way to proceed was to first decide whether the applications would be granted or not. Panel members consequently faced considerable opposition at the later conditions hearing from submitters who contested the primary decision.
The approach of the MDC once the hearing started was also criticised. Unusually, no officer reports were appended to the s42A staff report, and this led to an unsuccessful attempt by TPL to prevent two council staff and two peer reviewers presenting evidence to the panel. Also there were no MDC consents staff present at the conditions hearing. Instead the council predominantly relied on a detailed written memorandum from the s42A reporting officer (who was present at the conditions hearing) that was supplied to the panel prior to the hearing. This memorandum outlined matters of concern about draft conditions proposed by TPL.
In the course of undertaking this review a series of key learnings emerged that have useful application for consent authorities generally regarding the processing of large scale consent applications. These include:
In addition to the learnings identified above, the review also highlighted some areas of potential legislative improvement that could warrant further consideration by MfE. These include:
1 These included Forest and Bird, Fish and Game, DoC and Save the Wairau among others.
2 The panel said on pp325 of their decision: “It will now be clear that we have granted the applications subject to conditions and it is now necessary to decide how we should go about formulating and drafting the necessary conditions”.