As outlined in Section 1, Transpower lodged NOR with seven Councils in the Auckland and Waikato regions to enable them to designate land for the construction, operation and maintenance of a new electricity transmission link (including substations and underground cables) between Whakamaru and South Auckland.
The seven territorial authorities who administer the land that the route of the proposed transmission line traverses are:
The overhead line would begin at the Whakamaru Substation and traverse land through the Taupo, South Waikato, Waipa, Matamata-Piako, Waikato and Franklin Districts, terminating at Brownhill Road in Manukau City. The route is some 185 km long and the proposed designation corridor is a minimum of 65 m wide (although in some places it will be wider to allow for conductor swing or specific design components). The line will cross local authority roads and State highways, the East Coast Main Trunk Railway Line, several streams and rivers (including the Waikato River), small areas of land owned by the Crown and some 297 private properties. The proposed transmission line route is illustrated in Figure 1.
The proposal also includes ancillary activities such as accesses to the route corridor when they are within the designated area, fencing, safety and directional signage, and the removal of the Arapuni to Pakuranga A 110kV (“ARI-PAK A”) line.
The NOR components of the project have been designed in stages as set out in Table 1 below. This is to take into account the timing of other National Gird improvements such as works on other lines and connections (i.e. the Otahuhu system hub), allows the project to meet the immediate requirements by 2011, and allows monitoring of demand growth and adjustment (if necessary) to the timing of subsequent stages.
Figure 1: Proposed Transmission Line Route
Table 1: North Island Grid Upgrade Notices of Requirement Components and Anticipated Commissioning Dates
Date |
NOR Location |
Work |
|---|---|---|
2008 to 2009 |
Otahuhu |
Construct a new 220kV substation and install voltage support equipment. |
2009 |
Overhead line route and other areas |
Decommission and commence removal of ARI-PAK A line. |
2011 |
Otahuhu |
|
|
Pakuranga |
|
|
Pakuranga |
|
|
Underground cable route (Pakuranga to Brownhill) |
|
|
Brownhill |
|
|
Overhead line route |
|
|
Overhead line route |
|
|
Whakamaru |
|
|
Whakamaru |
|
2015 to 2017 |
Otahuhu |
Install new equipment to terminate the cables from Brownhill. |
|
Pakuranga |
Further minor upgrade work at Pakuranga. |
2021 to 2023 |
Otahuhu |
Install new cable termination equipment. Install dynamic voltage support equipment. |
|
Brownhill |
Substation switchgear added at Brownhill. |
|
Underground Cable Route (Otahuhu to Brownhill) |
Underground 220kV cable sections from Otahuhu to Brownhill (two circuits) one in 2021 and the second in 2023. |
2027 |
Otahuhu |
Install further dynamic voltage support equipment. |
2028 |
Whakamaru |
Install new equipment. |
2029 |
Otahuhu |
Install further voltage support. |
2030 to 2031 |
Otahuhu |
Install further voltage support. |
|
Underground Cable Route (Pakuranga to Brownhill) |
Implement forced cooling of Pakuranga to Brownhill Cables. |
2033 |
Otahuhu |
Install new cable termination equipment at Otahuhu. |
|
Underground Cable Route (Otahuhu to Brownhill) |
Implement forced cooling of Otahuhu to Brownhill cables. |
|
Brownhill |
400kV substation developed. |
|
Overhead line route |
Overhead line operates at 400kV. |
|
Whakamaru North |
400kV substation developed. |
2037 to 2038 |
Otahuhu |
Install additional interconnecting transformer capacity. |
2040 to 2042 |
Otahuhu |
Install further voltage support equipment. |
Transpower has also lodged applications for a number of resource consents from the ARC and Environment Waikato, as detailed below.
Transpower applied for resource consents with the ARC in June 2007 for work associated with the construction and installation, use, operation and maintenance of a new 220kV underground transmission cable between the Pakuranga Substation and Brownhill Road, and for works that are proposed to be located within the area of the Notice of Requirement for designation of the over head line section. The application also intrudes into the area of the NOR for designation for the Brownhill Substation.
In July 2007 Transpower applied for further resource consents from the ARC for work associated with the construction of towers for the new (400kV-capable) transmission line and ancillary works, including tower access and some topographic modification within the designated area.
Resource consent applications to the ARC are as follows:
Pakuranga to Brownhill Underground Cable Resource Consents
Overhead Line and Brownhill Substation Resource Consents
Transpower applied for the following resource consents from Environment Waikato in July 2007:
Overhead Line and Whakamaru North Substation Resource Consents