You are here: Publications > Resource management >
This document contains the evaluation for the Minister for the Environment required under section 32 of the Resource Management Act 1991 of the Proposed National Environmental Standards for electricity transmission. This evaluation considers the appropriateness, alternatives, costs and benefits of the proposed national environment standards. The document also reports on consultation under section 44 of the Act.
The New Zealand national electricity grid is owned and managed by Transpower. The majority of the grid was constructed before the Resource Management Act 1991 (the RMA) came into force and therefore has rights under the RMA to continue as an existing use. However, these rights do not apply to upgrading transmission lines. Transpower obtains resource consents for upgrading and some maintenance activities, as required by rules in district and regional plans.
This creates a number of problems, including the costs of processing resource consents, delays and uncertainty caused by the lack of consistency in plan rules (consent requirements for transmission activities vary significantly between district plans), and often a lack of specific provisions for transmission activities.
The Ministry for the Environment is addressing these problems by providing greater central government leadership and direction. The National Policy Statement on Electricity Transmission (the NPS), which took effect in April 2008, addresses the variable recognition of the national benefits of electricity transmission in plans and council decision-making. To give effect to policies and objectives set out in the NPS, councils must notify and process a plan change or review by April 2012.
The National Environmental Standards for Transmission Activities (NES) would help councils to implement the NPS within specified timeframes by providing a set of nationally consistent rules. The rules would take immediate effect without going through the plan change process, and would reduce RMA costs associated with transmission activities. The rules would also significantly reduce Transpower’s plan advocacy costs and the costs of RMA approvals. The net benefits over 10 years are estimated to be between $4.8 and $5.5 million (net present value), and the benefit−cost ratio at between 5.6 and 6.0.
The benefits of the NES derive from lower RMA costs associated with transmission activities. The reasons for the reduction in costs and the way the NES satisfies the selection criteria are set out below. The NES would:
The costs identified for the NES occur within the first three years, as follows.
Under the status quo, the community, councils and other agencies will incur costs, starting in 2008 and increasing through 2012, from becoming familiar with and implementing the NPS. The status quo is not simply a projection of historical costs: it is a projection of the new costs associated with the NPS.
The cost−benefit analysis also demonstrated that the financial output is sensitive to the percentage of councils wanting to incorporate the regulations into plans through a public consultation process, and to the level of Transpower’s activity. Transpower has recently announced a $50 million upgrade programme to maintain and strengthen structures on the national grid.1 The programme will bring forward required maintenance work that had been planned over the next 10 years. Therefore, benefits from providing national consistency and regulatory certainty by the transmission activities NES may be underestimated in the cost−benefit analysis.
1. See: http://transpower.co.nz/n2404.html (16 February 2009)
December 2009
Ref. ME 952