Text description of figure
The flowchart shows the following process:
- A desktop study is carried out by the regional council to identify homeowners that will be required to hold a WOF.
- WOF inspections are carried out on properties with on-site systems that are required by the regional council to hold a WOF. The inspection covers the matters described in section 5.1.1
- If the system passes a WOF will be issued and a re-inspection date set for three years time.
- If the system fails the homeowner will be required to fix the problems identified by the inspection within a set time limit.
- If the problems are fixed then a WOF will be issued. This may or may not require a further inspection depending on the reason for the initial failure.
- If the problem is not fixed within the time limit or repair or remediation is not possible, then the council will decide the next steps