You are here: NES Electricity Transmission Regulations > Overview
This overview answers the following questions:
Since 14 January 2010, the National Environmental Standards for Electricity Transmission (NES) apply to work on existing transmission lines and prevail over plan rules – section 43A(5) of the RMA. From this date, councils must observe and enforce the NES, to the extent their powers allow them to.
The NES takes precedence over relevant rules in district plans (and some regional plan rules) because:
However, a rule can permit an activity that is permitted by the NES, but can only address different effects from those addressed in the NES – section 43A (5) of the RMA.
Generally, the NES will set out the consent requirements for a project. However plan rules still apply if they cover an activity that is excluded from the NES (see table). The following rules will still apply:
Section 44A of the RMA requires councils to amend their plans "as soon as practicable" to remove rules that duplicate or conflict with the NES. A plan rule conflicts with the NES if the rule is more restrictive or more lenient than the NES.
Councils do not need to go through the usual RMA consultation process to bring their plans in line with the NES. Once councils have amended their plans, there should be no confusion between the plan and the NES requirements.
Most transmission maintenance and upgrade projects will consist of a range of activities. As such, activities may range from being permitted, controlled, restricted discretionary, discretionary or non-complying. For each project, Transpower will need to apply for a variety of consents, and may choose to apply for certificates of compliance for activities permitted by the NES.
Steps:
In determining whether a consent is needed under the NES, consider:
The NES does not alter whether the matter would be dealt with by a territorial authority or regional council. Land use matters normally dealt with by a territorial authority will still be dealt with by a territorial authority, and regional matters such as discharges will still be dealt with by the regional council. Unitary authorities will continue to deal with both territorial and regional consent matters.
Matters such as earthworks and vegetation may be split differently between district and regional councils in different areas. However, in general the following applies:
In considering a suite of applications for a transmission project, council officers must, subject to Part 2 of the RMA, have regard to the matters listed in section 104 of the RMA. They must report to council on these matters to inform council's decision on:
In making decisions on consent applications, the council must also have regard to the National Policy Statement on Electricity Transmission.
While objectives, policies and methods in plans and proposed plans are relevant for council’s decision, these should be considered in light of the NPS objective and policies. The NPS provides the policy framework for the NES.
In some circumstances, Transpower may apply for certificates of compliance for undertaking routine works in some circumstances. Section 139 of the RMA enables councils to issue certificates of compliance where a national environmental standard makes an activity lawful without a resource consent.
Existing-use rights will apply in the same way to activities established as permitted activities under the NES, as they do to activities established as permitted activities under district plan rules.
Existing use certificates (EUC) can still be sought under section 139A of the RMA. The existing use rights provisions of the RMA - section 10, section 10A, section 10B and section 20A - apply to activities that were lawfully established before the NES came into force. Section 43B(9) establishes that an NES provision that requires a resource consent be obtained should be treated as if it were an operative rule in a plan - section 10, section 10A, section 10B and section 20A.
The NES applies to any resource consents sought after the NES took effect on 14 January 2010. If a consent application was lodged before the NES was notified in the Gazette (17 December 2009), but the council had not decided whether to notify the application by that date, the NES prevails (ie, the NES applies to the consent application) – section 43B(7) of the RMA.
For resource consents where the decision on whether to notify the application was made before the NES was notified in the Gazette, the consent will prevail (ie, take precedence) over the NES – section 43B(7) of the RMA.
Any resource consents granted before the NES was notified in the Gazette continue to prevail – section 43B(5) and (6) of the RMA.
Coastal, water and discharge permits will also prevail over the NES, if they were granted before the NES was notified in the Gazette; however, this is subject to the ability of the consent authority to review the permit's conditions under section 128(1)(ba) of the RMA.
Section 43D of the RMA outlines the relationship between an NES and a designation.
Existing designations for existing transmission lines: An existing designation takes precedence over the NES until it lapses or the conditions in it, relevant to the NES, are altered. However, there are specific instances where this is not the case; for clarity refer to section 43D of the RMA, particularly 43D(3).
Designations sought for existing transmission lines after NES commenced (later designation): The NES will prevail over any further designation that Transpower seeks for an existing transmission line.
NES and designations for new lines: There is no direct relationship between the NES and a designation for new transmission lines. The NES does not apply to new lines.
Last updated: 18 January 2010







