Activities that may make up a transmission activities project:
Project description: A developer has asked Transpower to take a 600-metres-long section of an existing 110kV line in a residential area underground, as part of a major subdivision project.
Activities required to complete project:
The electric field associated with the new underground cables will be zero. The magnetic fields will be as follows:
| Configuration | Current rating (ampere) | Magnetic field 1m above ground level (milligauss) | Magnetic field at ground level (milligauss) |
|---|---|---|---|
| Trefoil 0.08m spacing | 525 | 24.6 | 94.0 |
| 365 | 17.1 | 65.3 |
| Main activities | Status under NES |
|---|---|
| Undergrounding existing overhead line | Controlled by regulation 12: the electric and magnetic field (EMF) has been modelled and complies with limits in regulation 10. Subsequent work on underground conductors will be permitted under regulation 11 if all applicable EMF conditions in regulation 10(2) to (8) are met. |
| Termination towers | Termination towers are included in the definition of undergrounding, and covered in general terms by regulation 11. The specific provision in regulation 15(3) clarifies that termination towers are controlled only if the provisions in regulation 14(3), (4) and (7) are complied with. These conditions limit height increase, proximity to buildings, and replacing a pole with a tower. However, a termination tower does not have to be placed within the envelope for permitted activity of an existing tower and there is no limit on the increase in base footprint. Once in place, termination towers are treated as normal towers. |
| Lightning rods | A lightning rod is considered part of the tower, so adding lightning rods is permitted by regulation 14. The height limit is not relevant, because a lightning rod is not included in the measured tower height. |
| Temporary line deviation | Permitted by regulation 17 (2), provided time limits on erection and removal are met – regulation 17(4). |
| Temporary structures | Permitted by regulation 17, provided time limits on erection and removal are met – regulation 17(3). |
| Removal of overhead line | Permitted by regulation 19 provided the site is restored – regulation 19(2) and (3). |
| Other potentially relevant activities | Status under NES |
| Earthworks and vegetation clearance | Earthworks and vegetation clearance are permitted, provided all of the relevant conditions in regulation 30 and regulation 33 are met. |
| Signs on support structures | Signs are permitted by regulation 23, provided conditions under regulation 23(2) and (3) are met. |
| Noise from machinery and implosive jointing | Noise from machinery and implosive jointing is permitted by regulation 37, provided it meets the limits in NZS6803:1999 Acoustics Construction Noise. |
Last updated: 18 January 2010