You are here: NES Electricity Transmission Regulations > Activities
These pages set out aspects of the NES that Transpower and councils need to consider for transmission activities.
By definition, support structures include associated hardware such as (but not limited to) insulators, cross arms or guy wires. The definition also includes the structure's foundations - see Existing lines. Any changes to the associated hardware will come within the NES provisions that address changes to transmission line support structures.
The NES defines tower height. Any earthpeaks or lighting rods are not included in the tower height, even though they are within the definition of 'support structure'. There are separate regulations covering telecommunications devices, and these are not part of the tower nor included in the tower height.
See examples of Existing lines and further information on activities carried out on support structures:
Work on transmission support structures that meet the conditions in regulation 14 is permitted. The regulation set out limits for altering and moving support structures to limit the effects.
The NES also defines a 'footprint' for the tower, and a base footprint, which is the footprint at 14 January 2010. For movement of towers, the NES defines an envelope for permitted activities, and an envelope for controlled activities. These envelopes are based on the tower footprint - refer to diagrams in the regulations.
The NES uses the base height, base footprint and envelopes to limit the distances that towers can be moved (or the footprint increased) or increased in height as permitted or controlled activities.
This regulation includes provisions which permit:
However:
If towers and poles are moved or altered in a way that does not meet the permitted or controlled activity conditions, the activity is restricted discretionary - regulation 16. The EMF conditions in regulation 10(2) to (8) must be complied with (except for termination structures as part of undergrounding or when part of a temporary line deviation).
The local authority has discretion to take account of any of the following matters in determining whether to grant the consent, and in setting conditions:
Work on transmission line support structures may require ancillary work and result in associated effects, such as tracking to access the lines, earthworks to create platforms for equipment, noise generated from the use of machinery or vegetation clearance. Tower relocation and maintenance works may be done in conjunction with other tower maintenance (eg, cleaning, painting and foundation works). As such, consents may be needed for some of these activities. A project involving tower maintenance or relocation could also involve work on conductors.
To work out other consents that may be needed for a project see
Refer to regulation 14, regulation 15 and regulation 16.
Refer to technical information on temporary structures and line deviation.
Temporary structures are a permitted activity, provided they are put up no more than 20 working days before the start of the project and removed within 20 working days after the completion of the project. A temporary structure may include hurdles and nets that are required for safety purposes, and lighting structures to facilitate night work - regulation 17.
If the structures are part of a temporary line deviation this is also permitted, and the structures must be put up no earlier than 60 working days before the start of the project and removed no later than 60 working days after the end of the project - regulation 17.
Temporary is not defined in the NES, so it takes its ordinary meaning: "lasting for only a limited period" (Concise Oxford English Dictionary 11th edition).
If the temporary structure or temporary line deviation does not meet the permitted activity conditions, it will be treated as a controlled activity - regulation 18. Control is reserved over:
If a section of transmission line is no longer required it may be removed, either completely or partly. This may include removal of the conductors and/or transmission line support structures. In many cases, it may be less damaging to leave tower foundations in place rather than undertake extensive earthworks to remove them. These activities are permitted, provided that the demolition material is removed and the land is restored - regulation 19. In the unlikely event that these conditions cannot be complied with, the activity is controlled - regulation 20. Control is reserved over:
Last updated: 18 January 2010
On this 'activities' page: Definitions of support structure and tower height
Associated activities that may need consent
Temporary structures and temporary line deviation







