The objective of the transmission risks NES is to establish consistent and reasonable controls on activities that could adversely affect the transmission lines, or pose a risk to the person undertaking the activity.
The proposed standard would set controls on activities carried out in the immediate vicinity of transmission lines that could adversely affect the lines or affect public safety. The proposed standard would apply to anybody other than the line owner undertaking activities adjacent to transmission lines that are not related to transmission operation, maintenance and upgrade. Earthworks and structures adjacent to transmission lines required as part of line maintenance and enhancement and undertaken by the line owner are controlled by the proposed transmission activities NES.
Plans cannot be more lenient than the NES. However, the NES will state that plans can be more stringent. A rule in a plan which covers the same activity as the NES (eg, subdivisions) will be able to be more stringent than the NES, and the matters for consideration listed in the plan rule will apply. For example, a plan could specify that subdivision is a restricted discretionary activity, whereas the proposed NES specifies that subdivision near transmission lines is a controlled activity. Where an activity is not addressed in the NES, the district plan rules would continue to apply.
Table A8 shows the detailed proposals and their relationship between the proposals and existing NZECP 34 provisions or district plan rules. A key difference between RMA controls and NZECP 34 is that NZECP 34 gives the line owner the discretion to allow activities, whereas under the proposed NES the local authority would have the discretion to grant or decline resource consents.
The proposed controls are based on existing controls in the mandatory code of practice for electrical safe distances (NZECP 34) and existing provisions in district plans under the RMA. Controls on excavating and depositing materials and building boat ramps near transmission lines, and on buildings and structures near transmission support structures, are based on the electrical safe distances and matters set out in NZECP 34. In addition, controls are proposed for subdivision within 20 metres of transmission lines, based on section 11 of the RMA. These controls are based on the existing requirements in district plans.
Two options are presented for buildings and structures near conductors:
Table A8: Proposed NES for transmission risks
View proposed NES for transmission risks (large table).
Circuit voltage |
Pole |
Tower (pylon) |
|---|---|---|
11 kV to 33 kV |
2 m |
6 m |
Greater than 33 kV and less than 66 kV |
6 m |
9 m |
Greater than 66 kV |
8 m |
12 m |
Circuit voltage |
Maximum span length |
Minimum distance beneath conductors under normal conditions |
Minimum distance to the side of conductors under normal conditions |
|---|---|---|---|
Not exceeding 33 kV AC |
125 |
7 |
8.5 |
Exceeding 33 kV but not exceeding 110 kV AC |
125 |
7.5 |
9.5 |
Exceeding 110 kV but not exceeding 220 kV AC |
125 |
8.5 |
11 |
275 kV DC and 350 kV DC |
125 |
8.5 |
7.5 |
Not exceeding 33 kV AC |
250 |
8 |
12 |
Exceeding 33 kV but not exceeding 110 kV AC |
250 |
8.5 |
12.5 |
Exceeding 110 kV but not exceeding 220 kV AC |
250 |
10 |
14 |
275 kV DC and 350 kV DC |
250 |
10 |
11 |
Not exceeding 33 kV AC |
375 |
9.5 |
20.5 |
Exceeding 33 kV but not exceeding 110 kV AC |
375 |
10 |
21 |
Exceeding 110 kV but not exceeding 220 kV AC |
375 |
11 |
22.5 |
275 kV DC and 350 kV DC |
375 |
10.5 |
18 |
All other spans |
Engineering advice required |
||
Notes:
Observance of potential conductor motion is required to ensure safe distances during construction.
Where supporting structures are not located on equal elevations, a specific engineering study may be required to ensure that distances are in accordance with Schedule 3.
Safe distance conditions |
Not exceeding 33 kV AC (bare or covered) |
Exceeding 33 kV but not exceeding 110 kV AC (bare) |
Exceeding 110 kV but not exceeding 220 kV AC (bare) |
Exceeding 220 kV AC or DC |
|---|---|---|---|---|
A: Vertically above those parts of any structure normally accessible to persons |
4.5 |
5 |
6.5 |
7 |
B: Vertically above those parts of any structure not normally accessible to persons but on which a person can stand |
3.7 |
4.5 |
6 |
6.5 |
C: In any direction (other than vertically above) from those parts of any structure normally accessible to persons, or from any part not normally accessible to persons but on which a person can stand |
2.1 |
3 |
4.5 |
5 |
D: In any direction from those parts of any structure not normally accessible to persons |
1.5 |
2.5 |
3.5 |
4 |
E: In any direction from the ground |
Refer to Schedule 4 |
|
|
|
|
Vertical distance to the ground (m) |
Radial distance (m) |
||
|---|---|---|---|---|
Circuit voltage |
Across or along roads or driveways |
Any other land traversable by vehicles |
Any land not traversable by vehicles due to inaccessibility |
In any direction other than vertical on all land |
Not exceeding 33 kV AC |
6.5 |
5.5 |
4.5 |
2 |
Exceeding 33 kV but not exceeding 110 kV AC |
6.5 |
6.5 |
5.5 |
3 |
Exceeding 110 kV but not exceeding 220 kV |
7.5 |
7.5 |
6.0 |
4.5 |
Exceeding 220 kV AC or DC |
8.0 |
8.0 |
6.5 |
5 |
Note: ‘Vehicles' includes mobile plant.