Office of the Minister for the Environment
Cabinet Policy Committee
Hon Trevor Mallard
Minister for the Environment
| Issue | Response |
|---|---|
| The presumption that transmission activities require resource consent unless specifically identified as permitted activities means that anything left off the list will default to discretionary. | The proposed NES now states that all transmission activities are permitted provided they comply with specific terms and conditions. If an activity fails to comply with the terms and conditions, the NES states what the activity type will be. An analysis of the potential effects of transmission activities and the terms and conditions imposed to control these effects has been undertaken to ensure that there are no significant adverse effects. |
| The proposals are extremely detailed and will over-ride provisions of district and regional plans. Councils are concerned about their ability to implement the NES (particularly the transmission risks NES proposals). | The lack of specificity in plans is one of the issues being addressed. Plans which are expressed in general terms are require extensive interpretation to determine what is permitted and what requires consent.The NES has been condensed and simplified to some extent, but it is inevitable that it will be more detailed than district plans.Guidance will be provided to assist councils implement the NES. |
| The proposals as written may generate more resource consents for transmission activities in some districts, which is not desirable for councils or Transpower. Other councils noted that the NES would be more lenient than their plans. | A review of plans has been undertaken and this showed that more consents may be required for placing transmission lines underground and new access tracks. Fewer consents would be required for dry abrasive blasting of tower foundations, increasing the current and voltage (provided ICNIRP guidelines are met) and increasing the height of transmission support structures. |
| The NES does not take enough account of the sensitivity of the environment the transmission activities will occur in. | The NES requires a high level of scrutiny for activities in sensitive environments or adjacent to sensitive land uses. |
| The NES does not contain limits for electric and magnetic fields. | The NES now includes a condition on electric and magnetic fields associated with increasing the current and voltage of transmission lines, and specifies how compliance with the ICNIRP guidelines will be demonstrated. |
| The NES will prevail over future designations, which could cause confusion for councils and Transpower in the future – for example, resource consents may be required as well as designation, doubling the workload associated with an upgrade. | The NES will only apply to existing transmission lines, not the construction of new lines or maintenance or upgrading of future lines |
| No provision has been made for minor discharges, nor for minor activities in the beds of lakes and rivers or coastal activities. | Some allowance has been made for these activities, subject to stringent terms and conditions. Many regional councils provide for such minor activities, particularly associated with existing structures, as permitted activities |
| The consultation is insufficient – it should include a second round of consultation on the NES. | Representatives from several local authorities and Local Government New Zealand were invited to participated in revising the proposed NES. Further input from local government and from key government departments will be sought at the legal drafting stage. No additional consultation step is proposed, because this proposed NES mainly affects Transpower and local authorities. |
| A number of issues were raised about interpretation and implementation of the NES | The Ministry will produce guidelines on implementing the NES, and propose to hold workshops (in conjunction with the implementation phase of the NPS on electricity transmission. |
1. The technical definition of the national grid is ‘the system of transmission lines, substations and other works, including the High Voltage Direct Current link, used to connect grid injection points and grid exit points to convey electricity throughout the North and South Island of New Zealand”. The NES will not apply to substations, and will only apply to the existing grid.
Last updated: 23 September 2008